1 Use

APV is used to appraise investments whose financing package disturbs the firm's existing capital structure (i.e. financial risk). It can also deal with a change in business risk.

It is often described as the "divide and conquer" approach in that it separates the "base" benefits of the project from its "side-effects".

APV is based on Modigliani and Miller's assertion that the value of a geared firm = value of an ungeared firm + present value of tax shield. Applied at a project level:

APV = Project value if all equity financed + Present value of the tax shield from any debt ± Present value of other side effects

2 Approach

(a) Calculate the operational value of the project as if it were being financed only by equity—"Base Case NPV".

(b) Calculate the present value of the "side-effects".

For example:

— value of the tax shield on interest on debt finance for the project;

— issue costs from raising external finance;

— value of government subsidies (e.g. loans received below commercial interest rates).

3 Critique of APV

Critics of APV point out that by valuing a project as a standalone entity it ignores the impact of a change in capital structure upon the value of the firm's existing operations.

The correct procedure would therefore be as follows:

1. Value the firm pre-project at its existing WACC.

2. Revalue the firm with the new project included, at the firm's post-project WACC.

3. NPV of project = 2 − 1 − cost of investment.

This type of stepped approach to valuation is particularly important is the case of large strategic investments (e.g. mergers and acquisitions).

我要纠错】 责任编辑:Sarah
打开APP 订阅最新报考消息

报考指南

今日热搜

热点推荐

热销好课

acca辅导课程

ACCA精品录播班

Get学霸同款

精品好课免费试听

ACCA-MA免费试听!

ACCA-MA免费试听!

申请购课优惠

正保会计网校ACCA

截图保存到相册

微信识别二维码

申请千元优惠

有奖原创征稿
客服 首页
取消
复制链接,粘贴给您的好友

复制链接,在微信、QQ等聊天窗口即可将此信息分享给朋友