问题

On 1 October 2009 Mocca entered into a construction contract that was expected to take 27 months and therefore be completed on 31 December 2011. Details of the contract are:

Plant for use on the contract was purchased on 1 January 2010 (three months into the contract as it was not required at the start) at a cost of $8 million. The plant has a four-year life and after two years, when the contract is complete, it will be transferred to another contract at its carrying amount. Annual depreciation is calculated using the straight-line method (assuming a nil residual value) and charged to the contract on a monthly basis at 1/12 of the annual charge.

 

The correctly reported income statement results for the contract for the year ended 31 March 2010 were:

The percentage of completion is calculated as the agreed value of work completed as a percentage of the agreed contract price.

Required:

Calculate the amounts which would appear in the income statement and statement of financial position of Mocca, including the disclosure note of amounts due to/from customers, for the year ended/as at 31 March 2011 in respect of the above contract.

(10 marks)

 

Answer

Mocca

Income statement year ended 31 March 2011

点击查看原文:试题>>   答案>>

正保会计网校20146月招生方案>>

 

我要纠错】 责任编辑:Sarah
今日热搜
热点推荐:
精品课程
acca辅导课程

ACCA精品录播班

Get学霸同款

精品好课免费试听
申请购课优惠

微信扫码咨询

申请千元优惠

ACCA-MA免费试听!

ACCA-MA免费试听
有奖原创征稿
取消
复制链接,粘贴给您的好友

复制链接,在微信、QQ等聊天窗口即可将此信息分享给朋友
客服