ACCA考试08年6月P1试题答案(6)

来源: 正保会计网校论坛 2010-08-11
普通

  (e) Control and sub-contractors

  Specifically in regard to the maintenance of internal controls when working with sub-contractors,the prominent difficulties are likely to be in the following areas:

  Configuring and co-ordinating the many activities of sub-contractors so as to keep progress on track. This may involve taking the different cultures of sub-contractor organisations into account.

  Loss of direct control over activities as tasks are performed by people outside R&M’s direct employment and hence its management structure.

  Monitoring the quality of work produced by the sub-contractors. Monitoring costs will be incurred and any quality problems will be potentially costly.

  Budget ‘creep’ and cost control. Keeping control of budgets can be a problem in any large civil engineering project (such the construction of the new Wembley Stadium in the UK)and problems are likely to be made worse when the principal contractor does not have direct control over all activities.

  Time limit over-runs. Many projects(again such as the new Wembley Stadium,but others also)over-run significantly on time.

  Tutorial note:only four difficulties need to be described.

[上一页]                  [下一页]

我要纠错】 责任编辑:肖肖
今日热搜
热点推荐:
精品课程
acca辅导课程

ACCA精品录播班

Get学霸同款

精品好课免费试听
申请购课优惠

微信扫码咨询

申请千元优惠

ACCA-MA免费试听!

ACCA-MA免费试听
有奖原创征稿
取消
复制链接,粘贴给您的好友

复制链接,在微信、QQ等聊天窗口即可将此信息分享给朋友
客服