Questions 1:

A company’s data are provided in the following 

Corporate Finance: Systematic risk of the project

The weighted average cost of capital (WACC) is closest to:

A 、 14.0%.

B、 11.5%.

C、  13.0%.

Questions 2:

When estimating the NPV for a project with a risk level higher than the company’saverage risk level, an analyst will most likely discount the project’s cash flows by a rate that is:

A 、determined by the firm’s target capital structure.

B、 below the WACC.

C 、above the WACC.

View answer resolution
【Answer to question 1】C

【analysis】

C is correct. Convert the D/E to determine the weights of debt and equity as follows:

Corporate Finance: Systematic risk of the project

A is incorrect because the debt is not tax adjusted when determining the WACC. WACC = 33.3% × 10% + 66.7% × 16% = 14.0% 

B is incorrect because the D/E is used as the weight for debt and equity. WACC = 50% × 10% × (1 – 30%) + 50% × 16% = 11.5%

【Answer to question 2】C

【analysis】

C is correct. If the systematic risk of the project is above average relative to the company’s current portfolio of projects, an upward adjustment is made to the company’s MCC or WACC.

 A is incorrect. The firm’s target capital structure is used to determine WACC, but in this case we need more adjustment in the company’s WACC. 

B is incorrect. If the systematic risk of the project is above average relative to the company’s current portfolio of projects, an upward adjustment is made to the company’s MCC or WACC.

成功=时间+方法,自制力是这个等式的保障。世上无天才,高手都是来自刻苦的练习。而人们经常只看到“牛人”闪耀的成绩,其成绩背后无比寂寞的勤奋。小编相信,每天都在勤奋练习,即使是一点点的进步,大家一定可以成为人人称赞的“牛人”。

点击了解更多CFA考试资讯>>

点击了解CFA无忧直达班>>

今日热搜
热点推荐:
CFA考试课程
CFA面授课程

CFA优享/旗舰面授课程

实时互动 备考无忧

大学生专享点击了解

CFA课程试听

扫码关注公众号
正保金融大讲堂

接收更多考试资讯

扫码找组织

有奖原创征稿
取消
复制链接,粘贴给您的好友

复制链接,在微信、QQ等聊天窗口即可将此信息分享给朋友
客服