A manufacturing company which produces a range of products has developed a budget for the life-cycle of a new

product, P. The information in the following table relates exclusively to product P:

Dingtalk_20210331142602

The company’s total fixed production overheads are budgeted to be $72 million each year and total machine hours
are budgeted to be 96 million hours. The company absorbs overheads on a machine hour basis.
What is the budgeted life-cycle cost per unit for product P?
$24·40
$25·73
$27·40
$22·73